80t Converter Steelmaking Project of Malaysia Eastern Steel's 2.7 MTA Project Successfully Put into Operation
On August 18, the 80t converter of Malaysia Eastern Steel Sdn. Bhd.'s 2.7 MTA project started hot commissioning. At 17:58, steel was successfully tapped out, marking the successful operation of the converter steelmaking project.
The Project's EP contractor is CERI. The main process facilities include: one 80t converter, one set of double-station hot metal pretreatment system (single-blown granular magnesium), one reserved 80t LF ladle refining furnace (No. 2 LF), and supporting public and auxiliary facilities.