The 35KV substation for environmental upgrading and modification project of 4.3m coke oven in Lianyuan Steel delivered power successfully

Date: 2022-12-16 Page View:0

 At 20:00 pm on Nov.17th, with the no-load impact on 35kv overhead line, the 35kv HV distribution device was supplied power, two main transformers were impacted and supplied power, and all 10kv HV distribution devices were supplied power finally, the 35kv substation for environmental upgrading and modification project of 4.3m coke oven in Lianyuan Steel which was contracted by CERI delivered power successfully.


   This contract was signed at the middle of March at this year, construction was kick off on Mar. 15th ,  all civil construction and installation of electric equipment were done on Aug. 30th, which past the preliminary acceptance by owner parties as schedule, and power was delivered successfully at one time on Nov. 17th . the successful power delivery of new constructed 35kv substation has laid foundation for environmental upgrading and modification project of coke oven in Lianyuan Steel, which is the fourth project that CERI has served for Lianyuan Steel, after the modification project of the neutral point grounding method of Lianyuan Steel Station I, diagnosis project of the power grid in the whole plant of Lianyuan Steel and the modification project of 220kV substation of Lianyuan Steel Station II.


公司官网新闻翻译2022-12-08-CN-EN-WN2551.png